Handover

The two-stage handover and deadline timers

How the handover gate works, the technical and final stages, and the clocks on the deadlines page.

  • Last reviewed

Every job is handed over in two stages, and a job cannot move on while required evidence is missing. The deadlines that follow commissioning each have their own clock.

The two stages

1. Technical handover. This is the day you hand the system over. Every required technical item must be done, or marked not applicable with a reason. That includes the building regulations notification when you are the notifier. Until then the job's handover panel reads Technical handover blocked and lists what is still open.

2. Final pack. This follows once the paperwork arrives: the MCS certificate or certificates, the building regulations certificate and the network operator proof. When the last of these is in, the job shows Final pack complete.

Steps: hand over a job

  1. Open the job from Jobs. The handover panel shows both stages, how many items are open in each, and the evidence completeness score.
  2. Press any open item in the list to go straight to it, or use Next step.
  3. When the panel reads Ready for technical handover, an admin or office user presses Record technical handover.
  4. The customer handover PDF and a customer link become available. If the customer has an email address on the job, they are emailed that the pack is ready.
  5. Add the final documents to their items as they arrive. The panel counts down what is left for the final pack.

The deadline clocks

Open Deadlines to see every clock across your jobs. The earliest open one on each job is tagged Soonest, and overdue ones are shown first.

ClockStarts fromAllowed
MCS certificate, previous schemeCommissioning10 working days (England and Wales bank holidays)
MCS certificate, MCS:2025Commissioning30 calendar days
Customer documents, MCS:2025Completion30 days
Building regulations notificationInstallation21 days for NAPIT; the 30-day legal limit is shown too
G98 notificationCommissioning28 days
G99 approvalInstallationOn or before the installation date
Complaint acknowledgementThe complaint2 working days

A PV and battery job has two certificates, so it has two certificate clocks. The cancellation period and consumer code registrations are shown where they apply.

Good to know

  • Office staff with deadline alerts switched on get an email when a clock is due soon or overdue.
  • Changing a recorded completion or commissioning date needs a reason, because it moves the clocks.
  • The evidence completeness score shows what is on file. It is not a judgement on the work: the Technical Supervisor signs off, and the certification body decides.