Construction phase plans for domestic solar installs

How CDM 2015 applies to domestic solar PV and battery jobs, what a proportionate construction phase plan covers, and how to get it read and signed on site.

Updated 7 minute read

The Construction (Design and Management) Regulations 2015, usually called CDM 2015, apply to all construction work, and fitting solar panels or a battery counts. Two points catch domestic installers out: every construction project needs a construction phase plan, and on a domestic job the client's duties usually pass to you.

Who has which duty on a domestic job

A homeowner having work done on their own home is a domestic client. Under CDM 2015, a domestic client's duties are normally carried out by:

  • the contractor, if there is only one contractor on the project; or
  • the principal contractor, if there is more than one contractor, for example you plus a scaffolding firm.

A scaffolder, roofer or electrician working for you is a contractor too. If you subcontract part of the job, work out who the principal contractor is before you start, and make sure everyone knows.

What the plan has to do

The regulations do not set a template. The HSE's expectation is that the plan is proportionate: a short, specific plan for a small job is better than a long generic one. It needs to set out how the work will be managed safely on this site. For a domestic solar or battery install, that usually means:

Project details

  • Address, start date and expected duration.
  • Who is in charge on site, and how to contact them.
  • Who else is involved: designer, subcontractors, scaffolder.

Site arrangements

  • Welfare: toilets, washing and drinking water. On a domestic job this is usually agreed use of the customer's facilities. Write down that it was agreed.
  • Parking, deliveries and storage, including where panels and any battery are kept before fitting.
  • Protecting the household and public: children, pets, neighbours and the pavement below the roof.

Hazards and controls

  • Work at height: access method, scaffold or tower details, edge protection, and who inspects it.
  • Fragile surfaces: roof lights, conservatory roofs, asbestos cement sheets.
  • Asbestos: whether the building could contain it (older buildings especially), and what you checked.
  • Manual handling: panels on ladders or scaffold, and heavy battery units.
  • Electrical: safe isolation of the existing supply, and the fact that PV arrays produce DC whenever there is daylight.
  • Battery hazards: arc flash, thermal runaway and fire, and where the battery is stored before installation.
  • Weather: wind limits for handling panels, rain and ice.

Emergencies

  • First aider and first aid kit.
  • Nearest A&E, checked for this address, not copied from the last job.
  • Assembly point and how to raise the alarm.

Getting it read and signed

A plan nobody has read does not protect anyone. Make reading it part of starting work:

  1. Issue the plan before the first day on site.
  2. Each person reads it and signs to say they have understood it, before they start work.
  3. Anyone arriving later, such as a subcontractor or a new starter, reads and signs when they arrive.
  4. If the plan changes, for example a new hazard is found, re-issue it and sign again.

Short daily pre-start checks and toolbox talks show the plan is followed, not just filed.

Notifying HSE

Most domestic solar jobs do not need to be notified to HSE. Notification applies to larger projects above a duration and workforce threshold. Check the threshold in the HSE guidance if you take on a large commercial job.

Common gaps

  • The plan is the last job's plan with the address changed.
  • The plan was signed after the work started.
  • The scaffold was provided by a subcontractor, but nobody agreed who the principal contractor was.
  • The battery arrived a week early and was stored somewhere that was never considered.

How Voltfile helps

In Voltfile, each job gets its own construction phase plan built from your template and a short site-details form. Only the questions that apply are asked: scaffold details only when there is a scaffold, and battery hazards only on battery jobs. Each person reads and signs on a phone, and daily checks and toolbox talks are recorded alongside. The install stage stays locked until the plan is issued and signed. See also battery installation paperwork.

The starting wording in Voltfile was written for the product. It is not HSE text and is not a legal opinion; review your template with a competent person.

Official sources

Always check the current version before relying on a date, a threshold or a form.

Free: the handover evidence checklist

A printable one-page-per-job PDF, from survey to final pack.

Get the checklist

More guides

See your next handover pack come together

Start a free trial, or book a 20-minute call and we will walk through a real job file with you.