G98 vs G99: which DNO route applies to your job?
The difference between G98 and G99 for UK solar PV and battery installs, how to work out the route from the combined capacity, and what evidence to keep.
Updated 6 minute read
Every solar PV or battery system that can run in parallel with the grid has to be made known to the local distribution network operator (DNO). There are two routes, set out in engineering recommendations published by the Energy Networks Association: G98 and G99. Choosing the wrong one is one of the most common, and most avoidable, paperwork mistakes on domestic jobs.
The short version
| Question | G98 | G99 |
|---|---|---|
| For | Small, fully type-tested generation | Everything above G98, or not fully type-tested |
| Limit | Up to 16 A per phase, in aggregate | Above 16 A per phase |
| When | Connect, then notify | Apply and get acceptance before connecting |
| Typical timing | Notify within 28 days of commissioning | Allow weeks; the DNO may need studies |
How to work out the route
1. Add everything up
The G98 limit applies to the aggregate at the premises, not to one piece of kit. Include:
- the new PV inverter(s);
- the battery's power conversion equipment, whether AC-coupled or hybrid;
- any existing generation already at the property, such as an older PV system.
2. Compare against 16 A per phase
The limit is a current, not a kW figure. On a single-phase 230 V supply, 16 A works out at roughly 3.68 kW, which is why you will hear "3.68 kW" used as shorthand. The current rating of the equipment is what counts: check the rated output current on the datasheets.
3. Check the equipment is fully type-tested
G98 relies on equipment being type-tested to the recommendation. If any part of the system is not, G99 applies whatever the size.
4. Watch for multiple installations
Where several G98 installations are planned close together, for example on a new-build development, the DNO usually needs to be asked before installation. Check your DNO's process.
Export limitation
If the aggregate is over the G98 limit, an export limitation scheme may let you connect more generation than you export. This is still a G99 matter. The DNO needs to accept the scheme, and the settings must match what was accepted. Keep the evidence of both.
The evidence to keep
- The calculation: what you added up and the ratings you used.
- For G98: a copy of the notification as submitted, the date sent, and the DNO's acknowledgement or reference.
- For G99: the application, the acceptance with its date, and any conditions such as export limits. The acceptance date should be on or before the installation date.
- Commissioning settings where the DNO set conditions.
The homeowner needs the network operator proof too. It is one of the key documents they should receive after completion, and their energy supplier may ask for it.
Common mistakes
- Adding a battery to an existing PV system and forgetting the existing inverter in the total.
- Treating 3.68 kW as the limit on a three-phase supply, or on equipment rated in current.
- Installing a G99 system on the strength of an application, before acceptance.
- Notifying under G98 and never keeping the acknowledgement.
How Voltfile helps
The G98 and G99 tracker in Voltfile records the route on each job. G98 is refused when the aggregate of new PV, battery and existing generation is over 16 A per phase. The G98 notice is counted from commissioning, and a G99 acceptance dated after installation keeps the item open. The DNO proof goes in the final pack and the homeowner portal. See also battery installation paperwork.
Voltfile does not submit notifications or applications. Use your DNO's portal or forms.
Official sources
Always check the current version before relying on a date, a threshold or a form.